Our customer SELECTION guide for new Homes

Below is a table itemizing all the selections you be making during the construction of your new home. This Table also denotes WHEN the selections are DUE based on the progress of work in the field. Click on links in the for the appropiate Selection item to navagate to a different page with SUPPLIER names, addresses, phone numbers and as well as PRODUCT links. Our forms and instructions for each of these selections are also on these individual pages for you to download and fillout. Selection FORMS must be signed and returned to us by the DEADLINES denoted below please!!
(NOTE: It is very important for you to fill out and return completed forms to us by the milestone deadlines noted below to allow us to order materials and schedule trades in time to prevent possible pauses and delays in construction.)
The items in this Selection Table are in the ORDER in which we typically NEED the information for construction. You may decide to do certain items early in order to coordinate with current selections BUT PLEASE remember we need the information per this sequence.
Item No.
Selection Description
Deadline of when Needed
Supplier and Product info. Instructions and Signoff Forms

1

House Layout & Tree Clearing
Before Tree Clearing
Selection #1 Link

2

Finalize Drawings
Before Digging Basement
Selection #2 Link

3

Windows & Exterior Doors/Front Door
At time of Basement
Backfill
Selection #3 Link

4a

Exterior Brick & Stone & Accessories
At time of Basement Backfill
Selection #4a Link

4b

Siding, Trim and Exterior Colors
At time of Basement Backfill
Selection #4b Link

4c

Shingles & Roof Accesories
At time of Wood Framing
Start
Selection #4c Link

4d

Metal or Specialty Roof (if any)
At time of Wood Framing
Start
Selection #4d Link

4e

Shutters and Other Ext Features (if any)
At time of Wood Framing
Start
Selection #4e Link

4f

Address Stone
(If any)
At time of Wood Framing
Start
Selection #4f Link

4g

Gutters and Downspouts
At time of Wood Framing
Start
Selection #4g Link

5

Garage Doors and Openers
At completion of Wood Framing
Selection #5 Link

6

Site Retaining Walls
At time of Roofing
Selection #6 Link

7

Basement Layout
At time of Roofing
Selection #7 Link

8

Hose Bib Locations
At time of Roofing
Selection #8 Link

9

Fireplace Units
At time of Roofing
Selection #9 Link

10a

Plumbing
(Part 1)
IN-WALL items
At time of Roofing
Selection #10a Link

10b

Plumbing
(Part 2)
Sinks, Faucets, Etc
Same as above OR At time of Drywall Prime Painting
Selection #10b Link

11

All Cabinets
At time of Roofing
Selection #11 Link

12

Appliances
At same time as #11-Cabinet Selection above
Selection #12 Link

13

Electrical Walk-Thru
At completion of Roofing
Selection #13 Link

14

Phone, CableTV, Security & Central Vac Walk-thru
At completion of Roofing
Selection #14 Link

15

Wood Floors
Prior to start of Drywalling
Selection #15 Link

16

Ceramic Tile & Marble
Prior to start of Drywalling
Selection #16 Link

17

Interior Doors & Interior Trim
Prior to start of Drywalling
Selection #17 Link

18

Misc Built-ins and Special Finish Carpentry & Mantels
During Drywalling
Selection #18 Link

19

Misc Specialty Items (Wine Room, Sauna, Pool, Etc.)
During Drywalling
Selection #19 Link

20

Interior Stone
(if any)
During Drywalling
Selection #20 Link

21

Interior Paint & Stain
At start of Wood Trim work
Selection #21 Link

22

Countertops
At start of Wood Trim work
Selection #22 Link

23

Carpeting & Vinyl Flooring
At start of Wood Trim work
Selection #23 Link

24

Light Fixtures
At start of Wood Trim work
Selection #24 Link

25

Acoustical Ceilings
(if any)
At start of Interior Painting
Selection #25 Link

26

Mirrors & Shower Doors & Misc. Glass
At start of Interior Painting
Selection #26 Link

27

Door Hardware & Cabinet Knobs
At start of Interior Painting
Selection #27 Link

28

Closet Organizers
At start of Interior Painting
Selection #28 Link

29

Landscaping, Brick Pavers, Etc.
At start of Interior Painting
Selection #29 Link

30

Driveway & Sidewalk Layouts
At start of Interior Painting
Selection #30 Link

31

Deck and Deck Railings
Typically within 6 weeks before end of project
Selection #31 Link

32

Shades, Blinds, Window Coverings
At completion of Interior Painting
Selection #32 Link

33

Miscellaneous & Other Items
TBD (if any)
Selection #33 Link